Ontario Holdback Release

Ontario holdback release planning should be tied to the project record, the invoice trail, substantial performance or completion status, published notices where applicable, and unresolved deficiencies or claims. Contractors should avoid treating holdback as an afterthought at final payment.

Holdback release workflow

  • Track contract price and holdback withheld
  • Record substantial performance or completion events
  • Keep proof of invoice delivery and payment history
  • List open deficiencies, set-offs, or disputed change orders
  • Prepare final invoice, waiver status, and closeout packet
Holdback calculator

Estimate the holdback and invoice clock.

Use this as a planning calculator only. Construction payment, lien, holdback, and notice rules depend on jurisdiction, contract terms, project type, and timing.

Holdback$10,000.00
Net payable before holdback release$90,000.00
Estimated payment dueChoose invoice date
Ontario non-payment notice checkpointChoose invoice date